Construction of 80,000m2 industrial subdivision including roads and services
Client
Shoalhaven City Council
Location
Yerriyong
Pascall Group were engaged by Shoalhaven City Council to construct Stage 5 of the Albatross Aviation Technology Park in Yerriyong.
Scope
The scope of works included:
Site establishment.
Implementation of management plans including WHSMP, CEMP incl. ESCP, QMP and TPMP.
Erosion and sediment control installation and maintenance including sediment basin and overflow weirs.
Service locating and survey set-out.
Clearing and grubbing of vegetation including working in conjunction with Shoalhaven City Council’s wildlife officer to implement fauna protection and tree removal protocols.
Environmental surveys and reporting prior to clearing works. Preservation of HBT’s and relocation of animals in accordance with wildlife procedures. Working with and around endangered species.
Bulk earthworks including excavation and shaping of overland drainage channels.
Pavement construction for road and taxiways including subgrade remediation works, primer seal and asphalt. Pascall Group constructed approximately 500m of roadways and 360m of taxiways.
Concrete works including kerb and guttering.
Service installation and commissioning including complete water, stormwater, sewer, electrical and communications.
Liaising with client and design team to work through design related changes.